91-1987review_HatterasYachts.pdf |
judicial review, 30 days, untimely filed, N.C.G.S. § 95-135(i), N.C.G.S. § 95-141, N.C.G.S. § 150B-45, Review Board Rule of Procedure .0602(d), Review Board Rule of Procedure .0605
|
2019-6111 Julio Cesar Lopez dba JC Masonry |
Wetsch
consent
confined spaces
Chapel Hill
29 CFR 1904.39
29 CFR 1926.55
20 CFR 1910.134
29 CFR 1926.1153
29 CFR 1910.1200
29 CFR 1926.1207
29 CFR 1926. 1203
29 CFR 1926.1204
|
2018-6034, 2019-6192 Petty Machine Company |
Tuttle
Gastonia
grinder
milling
guarding
guard
E3643 milling machine
Bridgeport model 250102
Nova Milling Machine 43L558
Nova Milling Machine 510025
abate
serious
infeasability
defense
NCGS 95-129(1)
general duty clause
29 CFR 252
29 CFR 1910.134
29 CFR 1910.1200
29 CFR 1910. 305
29 CFR 1910.1026
29 CFR 1910.334
29 CFR 1910.303
29 CFR 1910.219
29 CFR 1910.215
29 CFR 1910.212 |
2017-5972 Denise Smith dbs The Girls Company |
Garrett
29 CFR 1910.147
29 CFR 1910.212
abatement
abatement documentation
notice
acceptance
modification
|
2017-5973 Hibco Plastics |
Garrett
29 CFR 1920.147
29 CFR 1910.212
abatement
abatement documentation
notice of abatement acceptance
modification
|
2019-6090 Lindy Lee dba Tony |
Weaver
29 CFR 1910.132
Fayetteville
consent
contract workers
1099
tree felling
PPE
|
2019-6105 Baker Roofing Company |
Garrett
stipulation
fixed ladder
climb distance
trench rod
accuracy
29 CFR 1026.1053
estimate
Hendersonville
|
2019-6076 McLean Homes |
Garrett
head protection
eye protection
fall protection training
29 CFR 1926.100
29 CFR 1926.102
29 CFR 1926.501
29 CFR 1926.503
Belmont
|
2018-6007 American & Efird LLC |
Garrett
electric panel
SDS
29 CFR 1910.219
29 CFR 1910.303
29 CFR 1910.1200
|
2019-6134 Smith Rowe |
Weaver
consent order
Winston-Salem
trench box
29 CFR 1926.652
utility crew
safety meeting
audits
|
2019-6107 Cambridge Wilson |
Weaver
Emerald Isle
competent person
29 CFR 1926.501
29 CFR 1926.20
fall protection
slope roof
consent
|
2019-6213 FSC II, LLC dba Fred Smith Company, Inc. |
Weaver
Morrisville
300 logs
300A form
business hours
de minimis
appealed
29 CFR 1904.40(a)
NCGS 137(b)(3)
13 NCAC 07A.0301(h)(9)
employer checklist
deadline
non-serious
recordkeeping
record keeping
timely
|
2018-5995 Meritage Homes of the Carolinas, Inc. |
Koch
Charlotte
General Contractor
roof
guard rail
safety net
fall protection
site superintendent
photo
penalty
29 CFR 1926.501
appeal
|
2018-6106 Tripp Bro's. Inc. |
Weaver
Farmville
construction
29 CFR 1926.652
29 CFR 1926.651
29 CFR 1926.600
trench
excavation
competent person
checklist
electrical hazards
powerlines
de-energize
motion
consent
|
2019-6109 Hand 2 Hand Properties 8 Inc. dba Tom's Construction |
Weaver
Winston-Salem
29 CFR 1926.501
29 CFR 1926.25
29 CFR 1926.1052
repeat serious
penalty
residential construction
fall protection
fall hazard
|
2019-6128 Del Monte Fresh Produce N.A., Inc. |
Garrett
Whitsett
29 CFR 1910.147
29 CFR 1910.157
29 CFR 1910.303
hazardous energy
inspection
energy control
training
hazardous energy source
energy isolation
fire extinguisher
entrance
consent
lock out tag out
energy control plan
plug
|
2019-6179 American Granite-Carolinas, LLC |
Garrett
Charlotte
29 CFR 1910.178
29 CFR 1910.176
industrial truck
stone
consent
|
2018-6067 DH Griffin Infrastructure |
Garrett
warning sign
trench
pre-task plan
confined space permit
monitor
safety record
competent person training
PPE training
respiration protection
audit
29 CFR 1926.800
emergency response plan
boring
|
2018-5994 Lifetime Care Inc, dba Royal Oaks |
Garrett
amend
withdraw
|
2018-5989 Thompson Construction Group, Inc |
Garrett
Belews Creek
industrial construction
NCGS 95-129
29 CFR 1926.21
pipe
consent
|
2017-5971 Clapp's Nursing Center |
Garrett
Pleasant Garden
consent
29 CFR 1910.305
29 CFR 1910.1030
29 CFR 1910.23
29 CFR 1910.37
29 CFR 1910.147
29 CFR 1910.303
29 CFR 1910.334
29 CFR 1910.1200
|
2017-5947 Westrock Converting Company |
Garrett
Forest City
29 CFR 1910.212
JHA
job hazard analysis
press brake
training
bending
part bend pinch point
whipping
meet
consent
|
2017-5931 Summit Contracting Group Inc |
Garrett
Charlotte
29 CFR 1926.706
masonry wall bracing
training
consent
|
2017-5890 Custom Non-Woven Inc |
Gelbin
Thomasville
amputate
nip points
chain sprocket
lockout tagout
energy control
carding machine
melted plastic fibers
penalty
|
2017-5018 Beau Chene Company, LLC |
Garrett
29 CFR 1910.134
respirator
consent
|
2015-5749 Associated Scaffolding Company Inc. |
Garrett
KlimerLite
mast climbing platform
fatalities
Raleigh
scaffolding
multi-employer worksite
competent person
leasing
29 CFR 1926.451
consent
|
2016-5788 Guy Turner Review Commission Order |
Edwards
Pearson
Ward
protective equipment
carbon black
PEL
permissible exposure limits
29 CFR 1910.134
29 CFR 1926.55
respirator
QLFT
QNFT
qualitative fit test
quantitative fit test
|
2016-5845 NC State University Finance and Business |
Garrett
29 CFR 1910.269
electric
protective clothing
PPE
heat energy
Raleigh
Holladay Hall
high voltage equipment
consent
|
Brooks V. Alex Shugart |
NCGS 150B-34(b)
29 CFR 1910.142
29 USC 1802
Beechar R. Gray
Kenneth K. Kiser
Hugh M. Wilson
migrant workers
water supply
Yadkin County
garbage
farming
well
coliform bacteria
suspend assessment
affirm
orange books
89 DOL 0009
|
2018-5995 Meritage Homes of the Carolinas, Inc. Order of the Review Commission |
affirm
reasonable care
obvious
open
constructive knowledge
actual knowledge
reasonable duty
multi-employer
fall protection
residential construction
29 CFR 1926.501(b)(13)
general contractor
subcontractor
Koch
|
2018-6033 Steelfab |
Koch
steelfab
steel erection
Charlotte
collapse
death
injury
29 CFR 1926,20 (b)(2)
multi-employer
general contractor
fabricator
dismissed
|
2018-6037 Infrastructure Technology |
Weaver
dismiss
excavation
burden of proof
depth
trench
Raleigh
29 CFR 1926.651(c)(2)
29 CFR 1926.651 (g)(1)(iv)
|
2018-6061 Alpha Omega |
Koch
Carbarrus County
siding
construction
special emphasis
subcontractor
ladder
respiratory protection
written exposure control plan
respirable crystalline silica
intermediate employer
supervisory capacity
29 CFR 1926.1053 (b)(15)
29 CFR 1926.1153 (g)(1)(i)
29 CFR 1926.1153 (c)(1)
|
2008-4850 Burch Equipment |
Weaver
general industry standard
general duty clause
NCGS 95-129(1)
29 CFR 1910.1200
hard communications
written
hazardous chemicals
safety data sheets
sweet potatoes
farm
curing
storage
primary engagement
agricultural employee
exception
|
2018-6039 Lennar |
General Contractor
Subcontractor
Smith
Chambers
Dewberry
framing
fall protection
eye protection
pneumatic nail gun
head protection
affirm
due process
multi-employer
reasonable duty
open and obvious
reasonable diligence
in-person hearing
remote
videoconference
|
2019-6213 FSC II, LLC dba Fred Smith Company, Inc. Review Commission Order |
Smith
Chambers
Dewberry
29 CFR 1904.40 (a)
non serious
records
OSHA 300
timely production
de minimis
direct and immediate relationship
affirm
|
2019-6122 DR Horton |
Garrett
29 CFR 1926.501 (b)
serious
repeat serious
train
motion
agree
fall protection
construction
reclassify
reduce
amend
|
2020-6343 Sears Contract |
Garrett
29 CFR 1926.102(a)(1)
29 CFR 1926.453(b)(2)(v)
fall protection
serious
framing subcontractor
aerial lift
body belt
aerial basket
Cabarrus County
multi-employer worksite
reasonable duty
constructive knowledge
reasonable diligence
|
2018-6058 Lost Forrest 2021-NCCOA-587 |
OSHA 59
notice of contest
affirm
timely
timeliness
verbal notice
written notice
NCGS 95-137(b)(1)
13 NC Admin Code 7A.0802
reasonable business person
OSHRC Rule .0308(a)
motion to dismiss
Stroud
Inman
|
2018-6058 Lost Forrest Review Commission Order filed November 21, 2019 |
Edwards
Pearson
Smith
overturn
dismiss
interlocutory order
timely notice
contest
written notice
NCGS 95-137(b)(1)
|
83-1039 Rebarco |
concrete
defenses
electrical
knowledge
general duty clause
Barringer
isolated employee misconduct
Kiser
Curtis
|
83-1063 L.P. Cox, Inc. |
concrete
knowledge
nonserious
29 CFR 1926.701(a)(1)
Erdman
Houston
formwork
knowledge
|
2019-6177 James Walden dba JW Roofing and Associates |
Weaver
Gaston County
Construction
training
penalty reduction
consent
29 CFR 1926.501 (b)
29 CFR 1926.100
29 CFR 1926.102 (a)(1)
29 CFR 1926.503 (a)(1)
29 CFR 1926.1053 (b)(1)
|
2019-6120, 2019-6121 USC Inc dba United Canvas and Sling |
Weaver
stipulations
Lincolnton
follow up inspection
abatement
FTA
failure to abate
serious
29 CFR 1910.134
29 CFR 1910.95
29 CFR 1910.1052
29 CFR 1910.134
motion
regulators
air hoses
machine guarding audit program
consultative services bureau
lockout/tagout training
product changes
consent
|
2018-6035 Blackstone Shooting |
Wetsch
stipulation
consent judgment
firing range
29 CFR 1910.95
29 CFR 1904.32
29 CFR 1910.101
29 CFR 1910.157
29 CFR 1910.303
abate
firearms
PPE
personal protective equipment
reclassify
NRR
noise reduction rating
30dBA
hearing conservation program
Audiometric Testing Program
|
2019-6180 KMS Roofing |
Weaver
moonlighting
steep roofs
training program
repeat
Dismissed
29 CFR 1926.501
29 CFR 1926.503
|
Bradley Personnel 2019-6136 |
Garrett
NCGS 95-129(1)
General Duty Clause
Thomasville
host employer
silica
isocyanates
hazardous chemicals
PPE
Glue
fumes
.0541(a)
preponderance of evidence
temporary employees
TWI
temporary worker initiative
OPN 146
staffing agency
CPL 2-00.124
multi-employer citation policy
NCGS 195-136(a)
affirmative defense
walk-around rights
|
2019-6162 Eastwood Construction |
Garrett
construction
Belmont
multi-employer worksite
controlling employer
focused inspection
roof
plain view
ladder
eye protection
fall hazard
constructive knowledge
daily inspections
29 CFR 1926.102
29 CFR 1926.451
29 CFR 1926.452
29 CFR 1926.502
29 CFR 1926.1053
29 CFR 1926.403
29 CFR 1926.405
|
2020-6219 Lennar Carolinas, LLC |
Wetsch
Interlocutory Order
request for production
unredacted inspection file
NCGS 95-136(e)
NCGS 95-136(e1)
inspection report
redact
10 days
witness statements
affirmative defense
specific
mandatory
consent
discovery
redaction of names
denied
|
2019-6131 Lennar Interlocutory Order |
Wetsch
interlocutory
motion
production of unredacted inspection file
discovery
redaction of names
consent
mandatory
specific
witness statement
affirmative defense
10 days
redact
inspection report
denied
NCGS 95-136(e)
NCGS 95-136(e1)
good cause
particularized need
|